I have a task that is due to take 3 days but it will be completed over of
duration of 5 days.
Example: A task 3days but will be split during the week. Resource will work
on it Mon, Wed and Fri. How do I allocate the task time for this?
If I assign it as a 5 day, task resources will be requested to fill in
timesheets, which is not relevant.
Thanks in advance