TCPI Calculation in MS Project Pro 2003 server version

M

Monika

I am looking at TCPI in several projects and the values do not look like they
are being calculated correctly.

TCPI = BAC (or baseline cost) - EV (or BCWP) divided by EAC - AC (or ACWP)

I don't know what it is doing but in some cases I am getting an odd value on
many lines - 4294967295. And, on other lines when I don't get that odd
value, the value is not what I come up with when calculating it manually
based on the formula above. When I try to get help on the TCPI field in MS
Project, it gives me a help screen for CPI....

Can anyone provide guidance? Thank you.

Monika
 
Joined
Sep 14, 2011
Messages
1
Reaction score
0
TCPI Problem

Just go to VIEW tab and go to table in talbe go to more table. select Earned Value Cost Indicators.
Done.:D
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top