teaching project

Joined
Aug 27, 2012
Messages
1
Reaction score
0
hi,
I am working on a teaching project with the total duration of 5 years. Teachers are teaching verity of topics to our client's staff.

We do not know in ahead of time exactly when all the teaching courses will be offered during the next 5 years due to availability of the teachers, also, teachers may travel to the client’s site several times to finish a topic.

How can I use MS-Project for such project which tasks are not continuous and have unpredictable gaps?

Also, I need help on how to calculate the progress of such tasks.
Best,
PS. I am aware of recurring task concept, but not sure if that can help me :confused:
 