C
Cecilia Munguia
Hi!
I noticed that when I look at the availability for a team in PWA under
Resource Center, the capacity is 0hr or 8hr. I there a way to have a
view that shows me the capacity of the team combined in PWA. For
example, if there are 3 resources in a team, I'd like to see the
capacity of the 3 resouce as the Team's capacity - so, if the team's
members each has an 8hr a day capacity (8*3=24) the team's capacity
would be 24hr in one day.
I hope this makes sense and someone out there is able to help. Thank
you very much in advance.
Cecilia.
I noticed that when I look at the availability for a team in PWA under
Resource Center, the capacity is 0hr or 8hr. I there a way to have a
view that shows me the capacity of the team combined in PWA. For
example, if there are 3 resources in a team, I'd like to see the
capacity of the 3 resouce as the Team's capacity - so, if the team's
members each has an 8hr a day capacity (8*3=24) the team's capacity
would be 24hr in one day.
I hope this makes sense and someone out there is able to help. Thank
you very much in advance.
Cecilia.