A
Andy
I am using MSP 2002 Standard with 2002 Project Server. I have set up a
resource as a Team Lead and that resource has been delegating tasks. When
the resource with the delegated task sends an update to the Team Lead the
Team Lead still doesn't see any task updates on the update page, hence they
have no way to reject the update. All they can do is update the project
manager as to what their resource says was complete. The other option seems
to be to send a status request to the resource asking them to edit there
initial update. I have checked all of the permissions and it appears that
the lead should have plenty of access. Is the Team Lead suppose to be able
to Accept/Reject the task updates on the Update page as the project Manager
does?
Thanks in advance for any suggestions,
Andy
resource as a Team Lead and that resource has been delegating tasks. When
the resource with the delegated task sends an update to the Team Lead the
Team Lead still doesn't see any task updates on the update page, hence they
have no way to reject the update. All they can do is update the project
manager as to what their resource says was complete. The other option seems
to be to send a status request to the resource asking them to edit there
initial update. I have checked all of the permissions and it appears that
the lead should have plenty of access. Is the Team Lead suppose to be able
to Accept/Reject the task updates on the Update page as the project Manager
does?
Thanks in advance for any suggestions,
Andy