Team Member Project View settings.

R

Reuter

Using MP2003ent.

I currently have a group setting for (Team Members) to be able to view
projects their assigned to in PWA. Setup as: See Projects in Project center
and See Projects in Project views have been set to allow. Unfourtualy Team
Members are only able to view tasks that have been assigned to them and not
the entire Project. Please let me know what settings I may be missing or if
I should just create a separate group and call it "Team Members Project
View", if so how should I setup the new group?
 
D

Dale Howard [MVP]

Reuter --

Modify the My Tasks category to include at least one Project Center view and
one detailed Project view. Hope this helps.
 
R

Reuter

Outstanding, once again you came through.

Dale Howard said:
Reuter --

Modify the My Tasks category to include at least one Project Center view and
one detailed Project view. Hope this helps.
 