J
jearley
We are on Project Server 2003 SP2a and client SP2. We have a group
using project server who needs the ability to reject tasks so that
those particular tasks no longer appear on their timesheets. Scenario:
Team member is assigned a task. They know they will never work on
this task and immediately click "Reject" for this task. This team
member has never logged time to the task.
The project manager is able to see and accept the task rejection by the
team member. The PM then applies the task rejection to the project
plan. HOWEVER, after project processes the update, the team member is
STILL assigned to the task and still has the same amount of work.
Expected behavior: We're expecting after the PM processes the task
rejection that project would then remove that team member as being
assigned to the task and re-allocate the work to others assigned on the
task. If no others were assigned, the work and the assignment would be
entirely removed from the task.
Actual behavior: Project says that it has applied the update and
prompts you to save the file. However, everything looks EXACTLY the
same as it did prior to accpeting the task rejection. Therefore, when
you publish the plan again, the same task re-appears on the team
members timesheet again, as if it were never rejected in the first
place.
Is the expected behavior not correct? According to what little
information I could find in the various admin, PM and TM guides, it
implies this is what should happen.
Any help would be appreciated.
using project server who needs the ability to reject tasks so that
those particular tasks no longer appear on their timesheets. Scenario:
Team member is assigned a task. They know they will never work on
this task and immediately click "Reject" for this task. This team
member has never logged time to the task.
The project manager is able to see and accept the task rejection by the
team member. The PM then applies the task rejection to the project
plan. HOWEVER, after project processes the update, the team member is
STILL assigned to the task and still has the same amount of work.
Expected behavior: We're expecting after the PM processes the task
rejection that project would then remove that team member as being
assigned to the task and re-allocate the work to others assigned on the
task. If no others were assigned, the work and the assignment would be
entirely removed from the task.
Actual behavior: Project says that it has applied the update and
prompts you to save the file. However, everything looks EXACTLY the
same as it did prior to accpeting the task rejection. Therefore, when
you publish the plan again, the same task re-appears on the team
members timesheet again, as if it were never rejected in the first
place.
Is the expected behavior not correct? According to what little
information I could find in the various admin, PM and TM guides, it
implies this is what should happen.
Any help would be appreciated.