Hello,

I'm testing the Team Resource feature of Project Server 2007.
I created a Team resource including 3 human resources. For that I followed
the well detailed process explained by Dale Howard. Thanks again Dale!
I assigned this Team resource on an Activity plan, published the Activity
plan.
Then I expected that each human resource belonging to this Team could open
his/her Timesheet and see the new task. But this new task does not appear in
any timesheet.
What am I missing ?
Thanks for your help
 
M

Marc Soester [MVP]

Robert, the named resources that are part of the team will need to open "My
Task" and then they need to go to actions > assign team task ( the wording
may be a little different, sorry but I have no instance open). Only once the
named resource has done this step he/she can update the task.
Hope this helps
 