We are on MSPS 2007 and I have a work plan published with only the generic
team resource. There are no human resources on this sample plan.
I’ve followed the FAQs to establish a team resource. The self assignment
works well but the group tasks do no show in the My Task page of the
individuals. Here is the verbiage from the FAQs that is not working.
“When you publish a project with a Team resource assigned to tasks in the
project, the Team tasks appear on the My Tasks page of each resource that is
represented by the Team Resource. If the team members will work as a group on
the tasks, each of them can enter progress against the Team tasks.â€
Again, the self assign works so it looks like the team assignment is working
but when the human resources log in, there are no tasks in the my task page.
team resource. There are no human resources on this sample plan.
I’ve followed the FAQs to establish a team resource. The self assignment
works well but the group tasks do no show in the My Task page of the
individuals. Here is the verbiage from the FAQs that is not working.
“When you publish a project with a Team resource assigned to tasks in the
project, the Team tasks appear on the My Tasks page of each resource that is
represented by the Team Resource. If the team members will work as a group on
the tasks, each of them can enter progress against the Team tasks.â€
Again, the self assign works so it looks like the team assignment is working
but when the human resources log in, there are no tasks in the my task page.