Biggles
One of my users of the project database had a time out issue while trying to
save a file over the network. Project then created a temp project,
AUDIT_PLAN_TEMP. What do I do with that plan? I want to eliminate the TEMP
project without destroying what was already there. When I go into the
database with access, I see the tasks are still there for the original plan,
but when I open the original plan through project, there are only a few
tasks.
Is there some repair process I can use to get things back to proper state.