Hello,

I have a project plan however when I insert a new column text/notes I cannot
type any notes into the task level.

Anyone knows how to do this?
JBP
 
R

Reid McTaggart

If you inserted an Enterprise Project Text field, you can only enter data at
the project level (Task 0). If you want to enter task-level text, use an
Enterprise Text Field.

-Reid
 