Am using MS Project 2000. I want to show to the right of
a Gantt bar two items of information: the finish date and
the resource name. In other works I want to concatenate
two fields of information to appear to the right of the
bar.

How can this be done?

Thanks. Curt
 
R

Rod Gill

Hi,

Search help for custom formulas. Use a formula to concatenate the two fields
into say Text1 then in Format, Bar Styles you can show the Text1 field to
the right of your bars (under the Text tab).

--
Rod Gill
Project MVP
For Microsoft Project companion projects, best practices and Project VBA
development services
visit www.projectlearning.com/
 
J

JackD

Easiest way is to use a customized field.
From the tools menu select customize then fields. Choose an unused text
field.
Click the formula button and enter the following formula

[Finish] & " - " & [Resource Names]

Now format the bar to show the text field to the right of the bar.

-Jack
 