TF82010: This field is read only for the work item type "Requirement"

E

Evgeni Katsarski

Dear Sirs,
when I'm trying to change the start date of task which is already published
in VSTF, I'm receiving the mentioned error message. Is it possible in
general to change task details which already are published in TFS?


Thanks and best regards,
Evgeni
 
J

Jane Darnell

Evgeni,
I think you need to try this on a work item of type "bug" or some other
type. Apparently the "requirement" type won't let you change the start date
(I assume you are publishing the start dates FROM Project Server TO the TFS
machine). It sounds like you are further than me in getting your EPM<--->TFS
connection going.
Succes!
Jane Darnell
 