That other resource allocation number

G

Guest

I've found that sometimes project is assigning a second number to my
resource allocation inside the resource names column of my gantt chart. I
know that a single number in brackets (i.e., Robert[50]) dictates the unit
allocation, but sometimes I see two numbers seperated by a comma in those
brackets. What does that mean?

Thanks
 
G

Gérard Ducouret

Hello Robert,

The comma is just the decimal separator !
Mason[12,5] means that 12 full time and one half time mason are working on
the task.

Hope this help,

Gérard Ducouret
 