I've found that sometimes project is assigning a second number to my
resource allocation inside the resource names column of my gantt chart. I
know that a single number in brackets (i.e., Robert[50]) dictates the unit
allocation, but sometimes I see two numbers seperated by a comma in those
brackets. What does that mean?
Thanks