V
Vaso Vukovic
Hi Everyone,
these are more of a process question rather than technical - I have two
scenarios to which I'm struggling to get to the final/best answer:
1. How to 'Cancel' the project from PWA - e.g. Mid-May this year Project ABC
has reached stage 3 but the stakeholders determined it is no longer viable to
pursue and decided to stop all work. I need to save all actuals but do not
want this project coming up under timesheets for time entry or its tasks
coming up under 'My Tasks' for affected users any more.
2. How to close the project?? E.g. Project ABC has completed 100%, no more
active assignments exist. Yet it still comes up under 'My Timesheets' as an
option to enter time against?
these are more of a process question rather than technical - I have two
scenarios to which I'm struggling to get to the final/best answer:
1. How to 'Cancel' the project from PWA - e.g. Mid-May this year Project ABC
has reached stage 3 but the stakeholders determined it is no longer viable to
pursue and decided to stop all work. I need to save all actuals but do not
want this project coming up under timesheets for time entry or its tasks
coming up under 'My Tasks' for affected users any more.
2. How to close the project?? E.g. Project ABC has completed 100%, no more
active assignments exist. Yet it still comes up under 'My Timesheets' as an
option to enter time against?