L
Lazlo
H
I've been using the simplest way that I could find to determine the project end date. I have been linking all tasks together belonging to each resource in a start to finish manner. Most tasks aren't dependant on each other and it makes no difference when they're completed within the lifespan of the project. Therefore this seems to be one of the worst ways of scheduling tasks as resources often submit future tasks early and the earlier tasks may be completed last, which makes project think they're late
I've been let to understand that setting actual start dates for tasks isn't the best way for scheduling either
Can anyone advise me how to schedule a project when the tasks don't always need to be completed in a particular order, so that i may determine the end date of a project and then monitor its progress
thanks in advanc
Laura
I've been using the simplest way that I could find to determine the project end date. I have been linking all tasks together belonging to each resource in a start to finish manner. Most tasks aren't dependant on each other and it makes no difference when they're completed within the lifespan of the project. Therefore this seems to be one of the worst ways of scheduling tasks as resources often submit future tasks early and the earlier tasks may be completed last, which makes project think they're late
I've been let to understand that setting actual start dates for tasks isn't the best way for scheduling either
Can anyone advise me how to schedule a project when the tasks don't always need to be completed in a particular order, so that i may determine the end date of a project and then monitor its progress
thanks in advanc
Laura