A
Avi
PMs are getting the below warning message on their Project Plans.
"The resource is assigned outside the original dates for task ..."
"The duration of this fixed-duration task will change to accomodate the
resource assignment"
What happens is that the Task duration (mainly end date) gets increased
(moves forward).
We found out that this is happening because one or more resource(s) on the
task has planned admin time (in timesheets) and that is causing the duration
of the task to shift. Task type is set to Fixed Duration and resource are
fully allocated (100%).
Issue: PMs are confused as to why "Fixed duration" task are undergoing
duration change? They want the Task duration to stay unchanged and work or
units to change, in such case.
How can we avoid Task duration to shift in the above scenario?
Thanks!
"The resource is assigned outside the original dates for task ..."
"The duration of this fixed-duration task will change to accomodate the
resource assignment"
What happens is that the Task duration (mainly end date) gets increased
(moves forward).
We found out that this is happening because one or more resource(s) on the
task has planned admin time (in timesheets) and that is causing the duration
of the task to shift. Task type is set to Fixed Duration and resource are
fully allocated (100%).
Issue: PMs are confused as to why "Fixed duration" task are undergoing
duration change? They want the Task duration to stay unchanged and work or
units to change, in such case.
How can we avoid Task duration to shift in the above scenario?
Thanks!