the resource is assigned outside the original dates ...

Joined
Feb 17, 2017
Messages
1
Reaction score
0
Hi
I want to reschedule some tasks in MSP 2010 that have progress before but for this task MSP show me an error like this "the resource is assigned outside the original dates..." as mentioned in following . and finally in end of project for produce the Plan % for this tasks the Plan % not meet the 100%. why. please help me.
best regard.
Saeed.

upload_2017-2-17_21-23-24.png
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top