There are no data in MSP_VIEW_PROJ_ASSN_TP_BY_DAY

  • Thread starter Microsoft Communities
  • Start date
M

Microsoft Communities

Hi,

I use MSP 2003 Server

I scheduled by MSP 2003, and publish to project server. I input the actual
work on Project Web Access, and update task to my schedule. But when I
search the timephased data of tasks I just published, it not exist in
MSP_VIEW_PROJ_ASSN_TP_BY_DAY. Where are they? How can find them?

Because I need to view baseline work day by day, so I can't get timephased
data in MSP_WEB... tables (baseline work day by day in these tables does not
exist).

Thanks
 
M

Microsoft Communities

Hi,

After I had the "Expand timephased data in the database" option checked,
only data in MSP_TIMEPHASED_DATA is exist, but MSP_VIEW_PROJ_ASSN_TP_BY_DAY
is not

Thanks for support
 