We have a Master project plan with about 40 Project Server plans within it.
It is currently residing on the lan drive but calls all 40 plans from the
Project Server 2003 environment. This plan has been working well for over a
year or more.
Just recently, it started receiving the message " There is a problem with
the calendar name. The project you are opening has local base calendar names
that match the names of local base calendars in a currently open project.
These include Used for Microsoft Project 98 Baseline Calendar. To preserve
the calendars and scheduling, the existing local base calendars in the
project you are opening will be renamed."
Some background info: We are project server 2003 environment, no recent
changes to the enterprise global file were completed, no changes to the
enterprise calendars (we have 3 and have had 3 for many years), the server
configuration does not have a checkmark beside Allow projects to use local
base calendars.
Please let me know any suggestions you can provide on where to begin to look
for the culprit. We reviewed the organizer on the master plan and several
referenced Project Server plans within the Master Plan and they all have
enterprise named calendars.
Thank you for reviewing the long post
Trish
It is currently residing on the lan drive but calls all 40 plans from the
Project Server 2003 environment. This plan has been working well for over a
year or more.
Just recently, it started receiving the message " There is a problem with
the calendar name. The project you are opening has local base calendar names
that match the names of local base calendars in a currently open project.
These include Used for Microsoft Project 98 Baseline Calendar. To preserve
the calendars and scheduling, the existing local base calendars in the
project you are opening will be renamed."
Some background info: We are project server 2003 environment, no recent
changes to the enterprise global file were completed, no changes to the
enterprise calendars (we have 3 and have had 3 for many years), the server
configuration does not have a checkmark beside Allow projects to use local
base calendars.
Please let me know any suggestions you can provide on where to begin to look
for the culprit. We reviewed the organizer on the master plan and several
referenced Project Server plans within the Master Plan and they all have
enterprise named calendars.