This task is completed

D

Doc

When do "Completed" tasks disappear off the "Tasks" screen.

Tasks displayed: Current Tasks
%Work Complete: 100%
All updates have been accepted into the project plan.

The tasks seem to hang around the task screen sometimes - is there
somealgorithm, similar to the "10 day work up and coming" setting in
PWA configuration?

Regards
Doc
 
R

Rod Gill

Hi,

Are any other resources assigned to that task? The Task isn't complete until
all assignments are 100% complete
 