M
mike
Need: Customer would like to improve capacity planning for resources
using P.Server 2007.
Issue:Customer is unable to accurately identify the planned work hours
for tasks since most project are first time/first use
Result:Task Types are set to fixed duration, and resources are
assigned. The resource may only be needed for 2 hours, but are
assigned to tasks at 100% max units. Resources are assigned to
several tasks each day. All resources are over allocated.
Looking for any ideas as to how they could improve resourcing so that
the benefits of project server with regard to capacity planning can be
realized.
Thanks
using P.Server 2007.
Issue:Customer is unable to accurately identify the planned work hours
for tasks since most project are first time/first use
Result:Task Types are set to fixed duration, and resources are
assigned. The resource may only be needed for 2 hours, but are
assigned to tasks at 100% max units. Resources are assigned to
several tasks each day. All resources are over allocated.
Looking for any ideas as to how they could improve resourcing so that
the benefits of project server with regard to capacity planning can be
realized.
Thanks