S
Shane
I am using MS Project 2003, I also use 2007. I have a project that has within
it two tasks (A & B)which I need to start both on the same date, so if I
change the start date of task B, task A’s start date also changes to match it.
I have set task A as a predecessor of B and linked by Start to Start, but if
I change B’s start date A’s doesn’t change.
Please can anyone tell me how I can do this?
Thanks
it two tasks (A & B)which I need to start both on the same date, so if I
change the start date of task B, task A’s start date also changes to match it.
I have set task A as a predecessor of B and linked by Start to Start, but if
I change B’s start date A’s doesn’t change.
Please can anyone tell me how I can do this?
Thanks