S
Shawn Ericsson
Is there a way to get a task that is split between resources to not divide
the hours equally? For example, when we assign 100 hour task to two people,
it always splits the task 50/50. This creates a constraint issue if the max
allocation of one resource is 70% (duration is 9 days for 50 hrs) and the
other is 20% (duration is 31 days). This pushes out other tasks if it is a
predecessor and it also creates gaps in the resoure capacity (the 70% guy
would have 22 days slack time if he couldn't move on until the 20% guy was
done).
To alleviate this, we would make two tasks, assigning the 20% resource to 22
hrs and the 70% resource to 78 hrs. This would have them both finishing in
~14 days. What I'm looking for is a way to have Project maximize resource
utilization and when you put 100 hours down and two resources, it would divvy
up the hour split to get it done in 14 days rather than 31.
We are using Project 07, Server 07 (SP2) using Enterprise resources and
fixed work.
Thanks again for all of your help out there!!
Shawn
the hours equally? For example, when we assign 100 hour task to two people,
it always splits the task 50/50. This creates a constraint issue if the max
allocation of one resource is 70% (duration is 9 days for 50 hrs) and the
other is 20% (duration is 31 days). This pushes out other tasks if it is a
predecessor and it also creates gaps in the resoure capacity (the 70% guy
would have 22 days slack time if he couldn't move on until the 20% guy was
done).
To alleviate this, we would make two tasks, assigning the 20% resource to 22
hrs and the 70% resource to 78 hrs. This would have them both finishing in
~14 days. What I'm looking for is a way to have Project maximize resource
utilization and when you put 100 hours down and two resources, it would divvy
up the hour split to get it done in 14 days rather than 31.
We are using Project 07, Server 07 (SP2) using Enterprise resources and
fixed work.
Thanks again for all of your help out there!!
Shawn