time behind report

G

greg

Is there some kind of canned report or something that can tell me how far
behind a project is?

For example. Say today is 1-26-2009
I have
Task1 - finish 1-19-2009
Task2 - finish 1-22-2009
Task3 - finish 1-28-2009

So I would have
Task1 = 5 days late
Task2 = 2 days late
Task3 = 0 days late

or something like this?

thanks for any help
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top