greg
Is there some kind of canned report or something that can tell me how far
behind a project is?
For example. Say today is 1-26-2009
I have
Task1 - finish 1-19-2009
Task2 - finish 1-22-2009
Task3 - finish 1-28-2009
So I would have
Task1 = 5 days late
Task2 = 2 days late
Task3 = 0 days late
or something like this?
thanks for any help