time booked to Admin Project tasks

A

Ashraf EK Dubai

Hello everybody,

I have noticed a problem with time recorded against Admin Project tasks.
Time entered in the grid (daywise) are summed up to the 'Work' and 'Remaining
Work' columns. The 'Actual Work' column shows '0'. We have EPM2003 (SP1).
Will appreciate your help/guidance.

Thanks.
Ashraf/EK Dubai
 
M

Manmeet Chaudhari

Hi Ashraf
When you first create a task, the Actual Work field contains "0 hrs" until
you begin tracking the project by entering percent complete or actual work.
As you enter percent complete, percent work complete, or actual work
information, Microsoft Office Project 2003 updates actual work for the task.

Hope this helps
 
A

Ashraf EK Dubai

I meant 'actual work entered' in the timesheet grid from Web Access is not
reflected in the 'Actual Work' column - instsead it is shown in 'Remaining
Work' column in Web Access. You seem to have not correctly understood the
problem I explained.
 