B
binder
Version: 2008
Operating System: Mac OS X 10.5 (Leopard)
I am trying to create a spreadsheet that will allow me to enter both start & finish times (either 12hr or 24hr clock format) and then calculate the total hrs worked. Usually, the start time is AM & the finish time is PM or sometimes AM of the next day. Or the start time may be PM & the finish time may be AM the next day. Once I have the hrs worked calculated, I need to multiply this figure by the hrly rate to produce a Pay Amount. I looked at the response to the other similar question but it did not help. Thanks for any insight on this one....
Operating System: Mac OS X 10.5 (Leopard)
I am trying to create a spreadsheet that will allow me to enter both start & finish times (either 12hr or 24hr clock format) and then calculate the total hrs worked. Usually, the start time is AM & the finish time is PM or sometimes AM of the next day. Or the start time may be PM & the finish time may be AM the next day. Once I have the hrs worked calculated, I need to multiply this figure by the hrly rate to produce a Pay Amount. I looked at the response to the other similar question but it did not help. Thanks for any insight on this one....