D
Dan
We have been collecting all the project information on a
stand-alone basis using Project Professional 2000. This
included information regarding actual hours per day.
Currently we are migrating all this information into
Project Server 2003. We will be collecting time (actual
hours per day) using the web access.
I have two questions:
i) When I import the project into 2003, I want to keep
the actuals and enable the time collecting feature. After
importing the project into server 2003, I get the
following message. "The actual work in "project
file.mpp" may be out of synch with actual work updated
from timesheets.
Do you want to synch with protected actuals when you save
this project?"
I do not want to synch with actuals from time sheets at
the time of publishing. They have no information as all
of them are blank. I would like to keep the hours worked
information from project at the time of publishing and
then going forward, I would like to collect it from Web
Access. How do I do this.
ii) Whenever I save the project or approve the submitted
time from individuals, I get the following error message.
Message Type : Publish New and Changed Assignments
" The manager cannot create the resource account
(0x8C040017)
Could you please let me know how to fix this error.
Any help is greatly appreciated.
Thanks,
Dan
stand-alone basis using Project Professional 2000. This
included information regarding actual hours per day.
Currently we are migrating all this information into
Project Server 2003. We will be collecting time (actual
hours per day) using the web access.
I have two questions:
i) When I import the project into 2003, I want to keep
the actuals and enable the time collecting feature. After
importing the project into server 2003, I get the
following message. "The actual work in "project
file.mpp" may be out of synch with actual work updated
from timesheets.
Do you want to synch with protected actuals when you save
this project?"
I do not want to synch with actuals from time sheets at
the time of publishing. They have no information as all
of them are blank. I would like to keep the hours worked
information from project at the time of publishing and
then going forward, I would like to collect it from Web
Access. How do I do this.
ii) Whenever I save the project or approve the submitted
time from individuals, I get the following error message.
Message Type : Publish New and Changed Assignments
" The manager cannot create the resource account
(0x8C040017)
Could you please let me know how to fix this error.
Any help is greatly appreciated.
Thanks,
Dan