Time entered on projects changing dates

H

Hizzie

We are running MS Project server 2003. My team enters in their time
via web access. Then then print out a copy and hand it to
accounting. One of the resources noticed that the time he entered in
for 2 weeks ago shifted to dates for last week. Thinking he just
entered them in on the wrong date he pulled out the copy of the
printed version and the correct dates are on there. I had one other
individual have this happen. They are moving their time back to the
correct date. Any ideas why this happened and how I can prevent it
from happening again?
 