V
Victoria
Hi, We are using managed time periods for starters. In one particular
project, local generic resources have been set up. When the Project Manager
tries to enter these resources' time in the Resource Usage view, a message
pops up asking to sync the actuals. If we say "yes" it wipes out all of the
local resource time entries and sets the task back to 0% complete.
any thoughts?
Victoria
project, local generic resources have been set up. When the Project Manager
tries to enter these resources' time in the Resource Usage view, a message
pops up asking to sync the actuals. If we say "yes" it wipes out all of the
local resource time entries and sets the task back to 0% complete.
any thoughts?
Victoria