A
Angel
I've been using MSP and the Portfolio Analyzer for years and I've never seen
this:
I have a plan where the total hours in the plan match what is in the OLAP
cube, the total time by resource also matches, BUT the daily entries are WAY
off. The problem is that we report our time monthly. I cannot figure out what
the problem may be; here are some details:
MSP 2003 system
We use managed time-periods and I have forced a sync with protected
actuals... I've even deleted the time out of the Resource Usage view table
and then forced a sync with actuals and then republished assignments (trying
to repopulate the Project tables). Then re-run the cube. No luck.
I created a new cube wondering if the current cube is corrupt. Same exact
data appeared in the new cube.
My only other thought is to save the file offline, delete it from the DB,
import, rebublish & overwrite existing timesheets. This is a general
activities plan that has tons of users though and I was hoping to avoid that.
Any other thoughts?
this:
I have a plan where the total hours in the plan match what is in the OLAP
cube, the total time by resource also matches, BUT the daily entries are WAY
off. The problem is that we report our time monthly. I cannot figure out what
the problem may be; here are some details:
MSP 2003 system
We use managed time-periods and I have forced a sync with protected
actuals... I've even deleted the time out of the Resource Usage view table
and then forced a sync with actuals and then republished assignments (trying
to repopulate the Project tables). Then re-run the cube. No luck.
I created a new cube wondering if the current cube is corrupt. Same exact
data appeared in the new cube.
My only other thought is to save the file offline, delete it from the DB,
import, rebublish & overwrite existing timesheets. This is a general
activities plan that has tons of users though and I was hoping to avoid that.
Any other thoughts?