D
Doug
I recently made a change to some hours within a project plan and
republished it using the "Overwrite Actual Work" option to push the
changes down to PWA. I didn't realize that there was pending time
submitted by resources against the project that had not been approved,
and now this time is gone out of PWA. Is there a way to get this time
back? Is this submitted but not approved time stored anywhere in a
database table that we perhaps backup? Other ideas? Thanks!! -Doug
republished it using the "Overwrite Actual Work" option to push the
changes down to PWA. I didn't realize that there was pending time
submitted by resources against the project that had not been approved,
and now this time is gone out of PWA. Is there a way to get this time
back? Is this submitted but not approved time stored anywhere in a
database table that we perhaps backup? Other ideas? Thanks!! -Doug