In my project, I have a resource (material) assigned to a task. I enter
actual costs (time phased) for this resource under the task when invoices
arrive. When I enter the time-phased costs for the resource, the actual costs
(total) for the resource and the task update properly. I also have a baseline
saved for the task.
The problem exists with a calculated field that I created. It shows the
remaining balance for the given task by subtracting the actual cost (task)
from the baseline for the task. This field will update correctly when
updating the time-phased resource costs up through a seemingly arbitrary
date. After that date, the actual costs for the resource and the task update
correctly, but the calculated field fails to change. Any ideas what is going
on? I have multiple tasks where this problem is occuring but other tasks
don't have the problem.
Thanks,
Todd
actual costs (time phased) for this resource under the task when invoices
arrive. When I enter the time-phased costs for the resource, the actual costs
(total) for the resource and the task update properly. I also have a baseline
saved for the task.
The problem exists with a calculated field that I created. It shows the
remaining balance for the given task by subtracting the actual cost (task)
from the baseline for the task. This field will update correctly when
updating the time-phased resource costs up through a seemingly arbitrary
date. After that date, the actual costs for the resource and the task update
correctly, but the calculated field fails to change. Any ideas what is going
on? I have multiple tasks where this problem is occuring but other tasks
don't have the problem.