S
Subramanian Vasudevan
We have a requirement that the Standard Rate of all our resources must be
allowed to vary from Project to Project. For example, suppose we define a
Labour resource called 'Carpenter'. For Project1, his would have quoted his
standard rate as $41/hour. But for another project, Project2, another
Carpenter might quote a standard rate of $50/hour. This all leads us to
choose Project Resources over Enterprise Resources. So ideally there would be
one Carpenter resource for each project.
But we also have the requirement of being able to make Tie-Phased actuals
updates on the work done by these 2 carpenters for the 2 projects. Statusing
Updates is not possible on Project Resources, which is why we are stumped.
As of now, we are creating a separate Carpenter Resource for each project
(name suffixed with some unique ProjectID) in the Enterprise Resource Pool
for whom the standard rates differ. This we feel is cluttering up our
Enterprise Resource Pool. Is there a better way of doing this? Is there a way
to record time-phased actual work data for Project Resources? We are able to
do it from Project Professional because it can handle the detailed schedule
of the plan.
allowed to vary from Project to Project. For example, suppose we define a
Labour resource called 'Carpenter'. For Project1, his would have quoted his
standard rate as $41/hour. But for another project, Project2, another
Carpenter might quote a standard rate of $50/hour. This all leads us to
choose Project Resources over Enterprise Resources. So ideally there would be
one Carpenter resource for each project.
But we also have the requirement of being able to make Tie-Phased actuals
updates on the work done by these 2 carpenters for the 2 projects. Statusing
Updates is not possible on Project Resources, which is why we are stumped.
As of now, we are creating a separate Carpenter Resource for each project
(name suffixed with some unique ProjectID) in the Enterprise Resource Pool
for whom the standard rates differ. This we feel is cluttering up our
Enterprise Resource Pool. Is there a better way of doing this? Is there a way
to record time-phased actual work data for Project Resources? We are able to
do it from Project Professional because it can handle the detailed schedule
of the plan.