M
Michael Glenn
Hi,
I have an issue where time-phased data becomes unsynchronized. For example,
0h work for a task on a particular day when viewing the project plan, but an
SQL query on time-phased data for the same task gives 0.25h. Is there some
way to force re-calculation of time-phased data?
Thanks!
I have an issue where time-phased data becomes unsynchronized. For example,
0h work for a task on a particular day when viewing the project plan, but an
SQL query on time-phased data for the same task gives 0.25h. Is there some
way to force re-calculation of time-phased data?
Thanks!