P
Paul harris
I wish to produce a time phased resource report only Using Text column data
fields and resources:
The Areas, Clients and Funding Sources identified in Text Columns
The report is required to shwo the Horizontal axis showing with Quarters,
Months or Weeks (a report for each)
The Vertical axis showing
One Text Column (Say Client)
Second Text Column (Say Funding Source)
Budget/Actual/To Complete
Resource Quantity and/or Resource Cost
No activity descriptions are required.
My understanding is after some experimenting that:
1. Analyze Time Scaled data in Excel does not export Resources
2. Exporting to Excel does not support timescaled data and long activities
that span multiple periods will not be split over periods
3. This report is not produced by Views without massive amounts of
irreverent detail
4. This report is not produced by Reports
Do anyone have a technique for simply creating this type of report?
fields and resources:
The Areas, Clients and Funding Sources identified in Text Columns
The report is required to shwo the Horizontal axis showing with Quarters,
Months or Weeks (a report for each)
The Vertical axis showing
One Text Column (Say Client)
Second Text Column (Say Funding Source)
Budget/Actual/To Complete
Resource Quantity and/or Resource Cost
No activity descriptions are required.
My understanding is after some experimenting that:
1. Analyze Time Scaled data in Excel does not export Resources
2. Exporting to Excel does not support timescaled data and long activities
that span multiple periods will not be split over periods
3. This report is not produced by Views without massive amounts of
irreverent detail
4. This report is not produced by Reports
Do anyone have a technique for simply creating this type of report?