H
Hopeful_1
I work in project 2007 Professional
How can I get my time phased table in resource usage to show the correct
amount of work that is remaining?
For example:
The time phased table is set up in two tiers. Months / weeks. Then listed
in the table is a cumulating number from when the project starts to when it
finishes. When updating % work complete, the time phased field does not
change. Please tell me what I’m doing wrong.
How can I get my time phased table in resource usage to show the correct
amount of work that is remaining?
For example:
The time phased table is set up in two tiers. Months / weeks. Then listed
in the table is a cumulating number from when the project starts to when it
finishes. When updating % work complete, the time phased field does not
change. Please tell me what I’m doing wrong.