I need to plan full-day work with two periods.
First work period start at 08:00 and finish at 20:00
Second work period start at 20:00 and finish at 08:00 on the next day.
In special calendar whithout dificults I can determine only first work
period. With second work period I have a problem: Project system say to me
"time of finish period could not be early time of start same period".
How I can to determine correctly night-work period?