I would like to utilize MSP to extract "time reporting" (i.e. actual work on
tasks per week, per resource).
What is the best way to do this? I know (I think) I will have to use the
export function because I will need to use Excel so I can manipulate it the
data.
Here is an example:
TASK = WRITE REPORT (estimated work per resource = 50 hours)
2 RESOURCES ASSIGNED (FIXED UNITS/NON-EFFORT DRIVEN)
Res #1/week #1 = Actual Work 20h
Res #2/week #1= Actual Work 15h
Res #1/week #2 = Actual Work 35h
Res #2/week #2= Actual Work 30h
After 2 weeks, task is 100% complete... Res#1 = 55h and Res #2 = 45h
Is this type of thing "standard" functionality for MSP?
Thanks, Kevin
tasks per week, per resource).
What is the best way to do this? I know (I think) I will have to use the
export function because I will need to use Excel so I can manipulate it the
data.
Here is an example:
TASK = WRITE REPORT (estimated work per resource = 50 hours)
2 RESOURCES ASSIGNED (FIXED UNITS/NON-EFFORT DRIVEN)
Res #1/week #1 = Actual Work 20h
Res #2/week #1= Actual Work 15h
Res #1/week #2 = Actual Work 35h
Res #2/week #2= Actual Work 30h
After 2 weeks, task is 100% complete... Res#1 = 55h and Res #2 = 45h
Is this type of thing "standard" functionality for MSP?
Thanks, Kevin