When I run a timescale analysis for BCWS & BCWP on the
month format I get a chart where the timescale is the 1st
of each month. My confusion is which month am I taking the
number for?.....for example if I look st the graph line
aligning with the 10/1 date mark and the BCWS figure is
$23K and the BCWP is $21.5K are those figures for the
entire month of September or October?

Steve
 
R

Rod Gill

Hi,

The timescaled data should be the same as the Usage view. Look at a usage
view and check figures. That should tell you.

--