J
JP
It appears that we must use managed time periods in order for the resource
manager to be able to approve time on projects if which he/she doesn't own.
I have 2 more questions.
1) During testing we set the managed time period date for a 2 year perions
and we want to change to a monthly basis starting with 1/1/06 - 1/31/06.
2) We were testing the Notify you manager of timeoff in PWA. The reauest is
not going to the resource manager. Of which we did set up the RBS structure
and the resource falls under the appropriate manager. Can you help me
determine why?
manager to be able to approve time on projects if which he/she doesn't own.
I have 2 more questions.
1) During testing we set the managed time period date for a 2 year perions
and we want to change to a monthly basis starting with 1/1/06 - 1/31/06.
2) We were testing the Notify you manager of timeoff in PWA. The reauest is
not going to the resource manager. Of which we did set up the RBS structure
and the resource falls under the appropriate manager. Can you help me
determine why?