Time Sheet Approval by the Manager

J

JungleBoy

Hi:

We are using Project Server and PWA. We close our time entry periods every
friday than the managers have approve the time. Is there a way so that the
time gets updated on the server once the resource enters it without the
managers approving it as sometimes the managers are not there and its a big
task for a manager when there are multiple projects. Can I change a setting
or something.

We are using Project 2003.

Any help will be apprecited?
 
D

Dale Howard [MVP]

JungleBoy --

Please do not cross-post your questions. We read all the Project and
Project Server newsgroups, and I already answered your question in the
Project Server newsgroup.
 
J

JungleBoy

Thanks Dale. Sorry for posting it at two places, I am new here and will not
do it again.

Thanks again.
 