G
Grant
How can I accomplish the following?
I assign task ABC to start 01/01/05 with duration of 5 days ending 01/05/05
I assign one resource 100% giving me Work of 35 hours (5 x 7 hours a day)
I publish the task
The resource now enters 30 hours of time on 01/07/05 using weekly time entry
in PWA timesheet.
This is submitted for approval.
I now update project progress and would like to see the following:
Task ABC to start 01/01/05 with duration of 5 days ending 01/05/05
Remaining work is 5 hours, Actual Work is 30 hours
I do not want project to automatically adjust my start, finish or duration.
I would like to make the determination as to what is happening to this task,
perhaps it is finished 5 hours early or perhaps there is a 5 hour part that
we can defer to a different time all together.
Thanks,
Grant.
I assign task ABC to start 01/01/05 with duration of 5 days ending 01/05/05
I assign one resource 100% giving me Work of 35 hours (5 x 7 hours a day)
I publish the task
The resource now enters 30 hours of time on 01/07/05 using weekly time entry
in PWA timesheet.
This is submitted for approval.
I now update project progress and would like to see the following:
Task ABC to start 01/01/05 with duration of 5 days ending 01/05/05
Remaining work is 5 hours, Actual Work is 30 hours
I do not want project to automatically adjust my start, finish or duration.
I would like to make the determination as to what is happening to this task,
perhaps it is finished 5 hours early or perhaps there is a 5 hour part that
we can defer to a different time all together.
Thanks,
Grant.