Time Sheet Task Outline Level

T

Texas Tonie

Quick question:

Is it possible to have 4 outline levels in your GANNT chart, but assign and
report on resource time on the 2nd or 3rd outline level (not entering a task
update)?

A challenged Texas Tonie
 
J

Jonathan Sofer

Generally speaking, you do not want to assign resources at any summary level
which is what would happen if you attempted what you stated below.

Jonathan
 
J

Jack Dahlgren

Jonathan is right about avoiding summary assignments, but yes it is
possible, but you should create a task at that level to track against. There
are issues related to summary task assignments, so a regular task would be
preferred. You will need to keep it synchronized with the duration of the
summary task manually.

-Jack Dahlgren
 
B

bjorn.walberg

Generally speaking, you do not want to assign resources at any summary level
which is what would happen if you attempted what you stated below.

Jonathan








- Show quoted text -

Can you please specify why it is a bad idea to assign resources to a
summary task?
Bjorn
 