G
Grant
Scenario:
Created a new task: Duration: 10 days Start: Oct 3 End Oct 19
Assigned this task to 100% to myself
Published the project plan
In Project Web I went to my timesheet and entered in time at 4 hours a day
between Oct 2 and Oct 19 until I had a total of 40 hours, 50% complete.
Updated timesheets
In Project I then updated project progress and accepted my entries.
My plan was then updated to the following for my task:
Duration: 12.13 days Start: Oct 2 End Oct 17 Actual Start Oct 2 Actual
Finish N/A Actual Duration 7.13 days Remaining Work 40 hours and % Complete
59%
I get why Start, Actual Finish, and Remaining Work are what they are but
what happened to the rest; Duration, End, % Complete, Actual Duration?
Created a new task: Duration: 10 days Start: Oct 3 End Oct 19
Assigned this task to 100% to myself
Published the project plan
In Project Web I went to my timesheet and entered in time at 4 hours a day
between Oct 2 and Oct 19 until I had a total of 40 hours, 50% complete.
Updated timesheets
In Project I then updated project progress and accepted my entries.
My plan was then updated to the following for my task:
Duration: 12.13 days Start: Oct 2 End Oct 17 Actual Start Oct 2 Actual
Finish N/A Actual Duration 7.13 days Remaining Work 40 hours and % Complete
59%
I get why Start, Actual Finish, and Remaining Work are what they are but
what happened to the rest; Duration, End, % Complete, Actual Duration?