Time Sheet View - Entry by Day

S

Simmons_RJ

The timesheet view currently allows the resource to enter time at the task
level (Actual and Remaining). Is there a way to allow the resource to enter
actual hours by day in the timesheet view?

Thanks!
 
D

Dale Howard [MVP]

Simmons_RJ --

You need to ask your Project Server administrator to change your company's
default method of tracking progress in Project Server. He/she will need to
do the following steps:

1. Log into PWA with administrator permissions
2. Click Admin - Customize Project Web Access
3. Select the "Hours of work done per day or per week" option
4. Select the "Force project managers to use..." option
5. Select the "Resources should report their hours worked every day" option
6. Click the Save Changes button

Once he/she has completed the above steps, each project manager will need to
open every one of his/her own projects, click Collaborate - Publish -
Republish Assignments, and then click OK. This will "push" the new method
of tracking to every user's timesheet for every project. Do know, however,
that the above steps will only affect UNSTARTED tasks on each user's
timesheet. Any task with progress will continue to use the old method of
tracking until it is complete. Hope this helps.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top