Is there a way to configure Project Server so that resources can log
their times for the last month only upto the 2nd of this month and
there after are not allowed to log their times for the last month ? So,
for example, a resource is allowed to log times against a project for
the month of Feb 2006 up to 3rd of March and then have no permission to
log their Feb times into the Project.

Any help is appreciated,
Thanks, Laxmi.
 
D

Dale Howard [MVP]

Laxmi --

The use of the Managed Time Periods feature locks past closed time periods
and future time periods, and restricts time entry into the current open
periods. Your Project Server administrator would need to set up the time
periods to match your time reporting needs. Hope this helps.
 