The user has entered time in May for the task. But when I open the task of
the user in Microsoft Project professional, it is showing in June. How could
it happen?

Please help.

Thanks
Deva
 
M

Marc Soester [MVP]

Hi Deva,

the time you see is that actual work or work? If it is work then it makes
sense since that can be compared to the "forecast work". I would expect that
you will see actual work only for may. Is that correct?
 
D

Dale Howard [MVP]

Deva --

Was the task originally scheduled to start in June? And are you using the
Percent of Work Complete or Actual Work and Remaining Work method of
tracking progress in Project Server? Let us know.
 