Hello Dear:
Would you please advise, how can I link the %complete to
the duration. I think this si the way to track my buffer
usage. Let me explian what I am looking for. My
duration for each project is the estimate with build in
buffer to secure my project timeline. What I am looking
for is when I update the progress I should be able to see
how much buffer to date I have or have not used.
Any set up or solution is appreciated
Regards,
Majid
 
R

Rod Gill

Hi,

That can be done using VBA, otherwise it's a manual process for you.

--
For VBA posts, please use the public.project.developer group.
For any version of Project use public.project
For any version of Project Server use public. project.server

Rod Gill
Project MVP
For Microsoft Project companion projects, best practices and Project VBA
development services
visit www.projectlearning.com/
 