Timeline based on number of days only and not dates.

T

TW

I am trying to do a timeline based on number of days only. So if there is a
date in the future, I want to show - 45 days for a task, 30 days for another
and show the cumulative day counts (regardless of date). I don't want to
display any dates at all. Is this possible?
 
G

GP

Hi,

It is easy to set the length of a task (From 0 to 45 for example),
changing the Shape Sheet.
But I couldn't find how to show the cumulative day counts although I
guess there is a formula...
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top